Suvarnabhumi » Airport Rail Link from Makkasan to Suvarnabhumi is way behind schedule
Tuesday, September 4th, 2007The multibillion-baht Airport Rail Link from Makkasan to Suvarnabhumi is way behind schedule and over budget.
Last week experts met to thrash out how it can be saved before banks pull their support.
State Railway of Thailand (SRT) deputy governor Nakorn Chanthasorn said the situation was critical.
“Originally, we were supposed to pay for the link after it was completed. The previous Cabinet resolved that we would pay up 990 days after work commenced,” he said.
“This means the State Railway of Thailand (SRT) needs to find as much as 22.6 billion Baht within the next few months. We are asking for a Cabinet solution.”
The link is meant to dash passengers from the centre of the capital to the new Bangkok airport in 15 minutes. Already Shanghai has its maglev (magnetic levitation) train to Pudong, Kuala Lumpur an airport express-rail service and trains zoom travellers from Incheon International and Gimpo airports to Seoul Station.
Bangkok’s link was originally due for completion on August 7 this year. About three months of trials would be required after that.
Last week it was calculated the rail link is almost 50 per cent behind schedule.
The project’s construction work is just under 54-per-cent complete. By now it should have been 98-per-cent done.
Work on electrical and mechanical systems is more than 70-per-cent finished but should be 96 per cent along the way.
Nakorn remained unsure about how much longer it would take before completion and what that would cost. A recent compromise between the SRT and the project’s builders secured an additional 463 days for construction.
Originally, the construction was to be paid for by contractors, who would be reimbursed by the state, with interest.
The latest number-crunching session calculated the project has cost 34.5 billion Baht, including interest. That is over budget by one third.
Now that the SRT has to cough up after 990 days from the start of building, the bill is an initial 22.6 billion Baht, including 1.4 billion Baht in interest. If the bill not paid, financial institutions could stop their support and construction will stop,” Nakorn said.
One option is to stretch the loan term to require payment when building is finished. That will incur the SRT an additional 1.4 billion Baht in interest charges. Another is to refinance.
SRT board chairman Siva Saengmanee said a decision is to be due later this year.
Leave a Reply
You must be logged in to post a comment.
Related Topics
- Suvarnabhumi airport railway construction deadline to be decided this week
- State Railway given one month to finish Airport Rail Link plan
- Suvarnabhumi Airport city railway link set to open early next year
- Airport Link railway system from Bangkok's inner city to Suvarnabhumi airport - News Update
- Airport Link trains will arrive from Germany this month
- Suvarnabhumi airport railway link builder asked for deadline delay
- Train connecting new international airport with central Bangkok to open next year
- Air India to take off from Suvarnabhumi Airport
- Airports of Thailand seeking a new President
- Air India
- Public Bus
- Malaysia Airlines
- Sound-proof house for people living near Suvarnabhumi Airport
- Civil Aviation Training Centre to supplying airport employee training
- Samui airport to become second international flight hub
- Ten candidates apply for chief executive of Airports of Thailand
- Surging traffic puts former Bangkok Airport ahead of Hong Kong and Changi
- Airport Features
- Airport of Thailand to push airlines back to Don Muang airport
- Runways cracks not resulting from the construction - Airport of Thailand will meet the cost
- Suvarnabhumi Airport completely prepared for 28 Sept. 2006
- Suvarnabhumi Aerotropolis plan would have pros and cons
- Transport minister calls for higher security at Suvarnabhumi Airport
- Focus on Safety and Security at Suvarnabhumi Airport
- Suvarnabhumi Airport State Agencies affirmed system readiness
- European arrivals via Suvarnabhumi Airport rose year-on-year to 2.1 million
- Airport Special Campaign: Thai Culture & Lucky Passenger
- Asian airport investment vital for regional growth: analysts
- Airports of Thailand offering big discounts on aircraft landing fees to airlines
- Airport of Thailand estimates B120 billion for noise compensation
- Thai Airways premium passengers to increase after Suvarnabhumi opens
- New AOT board to sue King Power
- Suvarnabhumi ranks 4th best airport in online travel magazine poll
- First flights to Suvarnabhumi Airport Thailand
- Minor problem on first day at Suvarnabhumi Airport
- Suvarnabhumi to build a low-cost passenger terminal costing 1.2 billion Baht
- JBIC interested in giving 5.6 Billion Baht loan for Suvarnabhumi Airport extension
- Thailand to be aircraft maintenance centre of Asia
- No housing zone grows to 10km around Suvarnabhumi Airport
- Air traffic up during Songkran Celebration
- New Airports of Thailand chief promoted
- Malaysian Airline to start at Suvarnabhumi Airport on Sept 28
- Passenger traffic to Thailand international airports rose
- Compensation improved for property owners affected by aircraft noise
- Thailand opens Asia's largest airport
- Advance IT systems ready at Suvarnabhumi Airport
- Expansion of Suvarnabhumi airport starts soon
- Suvarnabhumi Airport aims for global accolades
- Thailand's visa-free entry rules tighten
- No need to close airport said Deputy director of Suvarnabhumi Airport
- Bangkok Mass Transit to provide more private buses around airport
- Cabinet cancels Suvarnabhumi metropolis project
- TOT banks on Suvarnabhumi connectivity
- Don Mueang Airport reopened costs Airports of Thailand loss 70 Million Baht a month
- Non-aviation services could make more revenue for AoT
- Suvarnabhumi will run smoothly as Don Muang within two months
- Aircraft Avionics
- New Bangkok Airport up and running
- Thai Airways, American Express contract with UN agencies
- Bangkok Airways first flight success
- Transport panel will negotiate with residents affected by aircraft noise
- Tours of new Suvarnabhumi Airport terminals end Aug 15, 2006
- Opening Suvarnabhumi Airports is not easy
- Customs free zone split up at Suvarnabhumi Airport will be reviewed today
- Expected more foreign arrivals at Suvarnabhumi Airport
- Suvarnabhumi Airport's Immigration officers undergoing 'personality training'
- AOT Crisis Centre set up as Suvarnabhumi countdown begins
- Million-dollar toilets to be added at Suvarnabhumi Bangkok Airport
- Budget airlines submit flight plans Aug 17, 2006
- Royal celebrations lift visitor arrivals to Thailand in 2006
- Police to clean up unlicensed taxi and illegal tour guide at Suvarnabhumi Airport
- Governmenrt plans Suvarnabhumi Airport expansion
- Airport Express
- Airport Shuttle Bus
- Flood dyke sinking, in need of repair
- Car Rental
- Improving drainage systems around Suvarnabhumi Airport
- Deputy Transport Minister set to wipe out taxi queue mafia
- Novotel Suvarnabhumi Airport Hotel Opens
- Aircraft Maintenance Software
- Parking fees at Suvarnabhumi airport starting 16 December 2006
- Suvarnabhumi Public Transportation
- Public Taxi
- Aircraft Maintenance
- Moving to Suvarnabhumi
- Airport Limousine
- Residents around Suvarnabhumi airport accept deal on noise problem
- Affirms readiness of Suvarnabhumi Airport by Transport Minister
- Suvarnabhumi runway declared safe
- Bangkok Airways says fare hike to Koh Samui was unavoidable
- Battle of the Airtropolises takes off
- Private Buses
- Air Crew Coach
- Don Muang returns as Bangkok international airport
- 1 Year of the Bangkok's new international airport Suvarnabhumi near capacity
- Tour Group (ATTA)
- King Power Duty Free may cut shop size at airport
- Fewer Suvarnabhumi glitches on 2nd day of operations
- Private Vehicles
- Airports of Thailand may run own commercial area after terminating King Power contracts
- Suvarnabhumi Airport set to open on Sept 28, ( Thailand )
- KLM Thailand (Royal Dutch Airlines)
- Don Mueang Airport will turn to logistics hub
- Two-airport plan risk government's credibility
- Suvarnabhumi Airport Passenger Terminal Building
- Airports of Thailand board rejects plan to sell its stake in Airport Associate Co
- About Suvarnabhumi Airport
- Airports of Thailand to study Don Muang as a 2nd Bangkok international airport
- Demand for Novotel Suvarnabhumi Airport Hotel surged
- Deputy Prime Minister opposes Suvarnabhumi province plan
- Airports of Thailand plans commercial complex land at Suvarnabhumi Airport
- Bonded warehouse area at Suvarnabhumi airport to be expanded
- New AOT Board should take immediate action to repair runways and taxiways at Suvarnabhumi Airport
- Airports of Thailand to reserve seats and toilets in Suvarnabhumi Airport for monks
- Suvarnabhumi Airport boosts investment
- Air Purification System
- Suvarnabhumi Airport - to become regional hub
- THAI Air to Migrate to Suvarnabhumi Airport
- Airports of Thailand to revoke permanent passes of all King Power staff
- CTX scanners have been fixed & ready for full operation
- Thai Airways loses customers after moving back to Don Muang airport
- Meeting will be held to follow up problems at Suvarnabhumi Airport
- Private sector confident Suvarnabhumi’s cargo hub potential
- New board of Airports of Thailand to cover up loss during military government took control
- Thailand's airport imbroglio grows
- Suvarnabhumi Airport's Integrated Air Traffic Control System
- Airport Fees
- Suvarnabhumi Airport Bangkok ready for Megajet - Airbus A380
- "Suvarnabhumi Cash Card” to make traveling easier
- Energy consumption to jump after Suvarnabhumi Airport opens
- Airports of Thailand gave Loxley a month to improve security service at Suvarnabhumi
- Suvarnabhumi Airport welcomes massive number of passengers
- Trial for International Flights completed successfully
- Star Alliance backs THAI stand on airport, 'two sites too costly'
- THAI Air downgrades security vigilance for domestic & international flights
- International Pilots & Airlines reassure confidence for the new Bangkok airport, Suvarnabhumi
- Two aviation fuel pipeline operators set to go in court
- Aircraft Charters
- Nok Air starts early at new airport but opts out on big day
- Board of Thailand Airports has resigned
- Reopening 10 aircraft parking bays & scheduling B1-B2 taxiway to be repaired
- New government to force fare meters in taxis to protect passengers
- King Power files 68 Billion Baht suit against Airports of Thailand
- Dining at Suvarnabhumi Airport (Guide / Article)
- Energy-cutting measures at Suvarnabhumi help airlines save
- Don Muang airport may return as Bangkok second airport
- Airports of Thailand to make an initial 736 Million Baht for noise compensation
- Suvarnabhumi Airport ready to be a gateway to Asia
- Suvarnabhumi airport security tightened during festive season
- King Power denies its contracts abused law
- Aircraft Mechanic Schools
- Bangkok and Chiang Mai named top 10 best cities in the world
- King Power Duty Free back at Suvarnabhumi Airport
- New Bangkok Airport's a smash with Tammy
- Airports of Thailand terminated King Power Duty Free's contracts
- Airlines praise Suvarnabhumi airport
- Engineer: Repairs some areas should take only 2-4 weeks
- Burmese carrier launches flights to new Bangkok Airport
- CNN - New era for air travel
- Airports of Thailand will decide on Loxley's security contract today
- Discount storage fees possible for outgoing agricultural products
- Future opportunities for Suvarnabhumi
- Transport Minister to take ambassadors tour Suvarnabhumi Airport
- Transport Ministry says no return back to Don Muang
- Smooth operations at Bangkok’s Suvarnabhumi Airport
- Restrictions will be enforced on liquids, aerosols and gels in hand-carried luggage on all commercial flights
- 46 Diplomats confident in Suvarnabhumi Airport's capability
- Sept 7, Check-in system at Suvarnabhumi Airport Testing
- Thai Airways president opposes Don Muang as international airport
- Airports of Thailand told to buy land and buildings within 10km around airport
- Bangkok Airways early move to Suvarnabhumi, September 21, 2006
- Thai Airways to compensate Suvarnabhumi for plane's runway damage
- No Ceremonies for Don Muang close
- Bangkok Airways starts at Suvarnabhumi Airport on September 21, 2006
- Charter Flight
- Suvarnabhumi Airport to be opened on schedule
- Suvarnabhumi Airport needs expansion
- DCAP Confident Suvarnabhumi Airport will have Power
- Airport of Thailand to promote Suvanabhumi as Smile Airport
- No problem with holes in Suvarnabhumi Airport’s roof
- Air Charter Service
- Noise pollution around new Bangkok Airport will be concluded
- JAL to add flight after Suvarnabhumi Airport opens
- New Bangkok Airport contracts to be re-examined by Gen Saprang
- Airports of Thailand to cancel Suvarnabhumi Airport hotel contract
- International visitor arrivals increase at Suvarnabhumi Airport
- Land price rises near Suvarnabhumi
- Security system & staff set ready for Suvarnabhumi international airport
- CDRM special committee finds Suvarnabhumi prepared
- Army joined to protect royals at Suvarnabhumi Airport
- Fingerprint identification equipment to be installed at Suvarnabhumi Airport
- AOT helps communities affected by noise pollution
- Airline Lounge at Suvarnabhumi Airport received Best First Class Lounge Award
- In flight liquids to be strictly enforced on June 1, 2007
- Attractions around Suvarnabhumi Airport Prepared for Tourists
- Customs Department satisfied overall performance
- Some parking bays will close for repair
- Thai AirAsia switch to Suvarnabhumi early
- Amari Don Muang Hotel emphasizes meetings as customers move to the new airport (Guide / Article)
- Thai Airways satisfied with Suvarnabhumi Airport