Suvarnabhumi » Thailand’s airport imbroglio grows
Tuesday, September 4th, 2007Reports of damage to runways and tarmacs at Bangkok’s new airport have been significantly overblown, a government panel of engineers set up to investigate the problems said Friday.

“There are no cracks,” Suchatvee Suwansawat, the secretary of the panel, said as he stood over a section of asphalt cut up as part of the investigation. The main problem was ruts, not cracks in the asphalt, Suchatvee and other experts said, contradicting several weeks of reports in local media here.
“The cement base is fine. The problem can be fixed.”
While good news for the more than 40 million passengers expected to use Suvarnabhumi Airport this year, the findings may complicate efforts by Thailand’s military- appointed government to use shoddy construction at the airport as one of the justifications for the coup that ousted Prime Minister Thaksin Shinawatra, who pushed the construction project through during his five years in power.
Plagued by delays and allegations of corruption during four decades of planning and construction, Suvarnabhumi was touted as a regional hub that would take business away from airports in Hong Kong and Singapore.
But since opening in September, the airport has been criticized by travel agents and travelers for its overcrowded arrival and departure halls, lack of signage, long lines at immigration and lengthy walks to gates. The facility has been the focus of a fierce political firestorm, with the government accusing Thaksin of rampant corruption in the building of the airport.
An ally of Thaksin, Chotisak Asapaviriya, resigned Thursday as president of Airports of Thailand, the government-controlled company that manages Suvarnabhumi. Asapaviriya said the imbroglio over the airport had been so stressful that he needed to resign to maintain his health.
The panel of engineers said it was unusual for tarmacs at Suvarnabhumi airport to be damaged only four months after opening, but played down the magnitude of the problem. Reporters who accompanied officials Friday to what were described as the worst-affected areas saw ruts a few centimeters deep but only a small area with hairline cracks.
“This is a common type of damage. You see it in airports all over the United States,” said Noppodol Phien- Wej, a representative from the Consulting Engineers Association of Thailand and a member of the committee investigating the problems.
“What is unusual here is the scale of the problem and the speed it is happening.” About 70,000 square meters, or 84,000 square yards, amounting to 2.3 percent of the airport’s total pavement, is damaged, said Noppodol, noting that damage to the runways is “minute.”
The finding dovetails with comments from airlines that use the airport. “Everything is normal,” said James Ward, a spokesperson for British Airways. “So far we haven’t had any reported problems. Takeoffs and landing are normal. We haven’t heard any complaints from the staff.”
Thaksin was both credited for speeding up a project that had stalled and criticized for rushing it into completion.
“To say that all the corruption was confined to the Thaksin regime is exaggerated,” said Thitinan Pongsudhirak, a former consultant to Airports of Thailand who helped prepare the company for its listing on the stock market. “But most of the construction was done under Thaksin.”
Thitinan predicted that future investigations would reveal further problems and malfeasance. “What we are seeing today is just the tip of the iceberg.”
Every aspect of the project, Thitinan said, “the duty free concessions, the parking lost construction, the baggage system — has got something hidden underneath.”
“This airport is really the embodiment of all that was wrong with Thaksin: the corruption, cronyism, the hubris,” Thitinan said. “It’s reached a point where it’s not just a national embarrassment. It could collapse the aviation industry and the Thai economy could really take a hit.”
Initial plans for the airport date back four decades but the bulk of the construction was carried out during the administration of Thaksin, who was prime minister from 2001 until he was deposed in a coup last September.
With Suvarnabhumi running close to its capacity of 45 million passengers a year, the government will decide Tuesday whether to transfer some flights to the old airport, Don Muang, which today handles only charter flights. Proposals range from allowing low-fare airlines to use the old facility to reserving Don Muang for domestic flights. ( Uamdao Noikorn/Thomas Fuller - International Herald Tribune)

One Response to “Thailand’s airport imbroglio grows”
Leave a Reply
You must be logged in to post a comment.
Related Topics
- Focus on Safety and Security at Suvarnabhumi Airport
- PM eases Suvarnabhumi move timetable
- Thailand opens Asia's largest airport
- Suvarnabhumi runway declared safe
- Cabinet approves re-opening of Don Muang Airport
- PM Satisfies the Authorities's Performance on Suppressing Narcotics
- Suvarnabhumi Airport State Agencies affirmed system readiness
- Don Muang airport may return as Bangkok second airport
- Suvarnabhumi Airport set to open on Sept 28, ( Thailand )
- About Suvarnabhumi Airport
- Suvarnabhumi Airport aims for global accolades
- CNN - New era for air travel
- Bangkok's former Don Muang International Airport officially reopened for domestic flights
- First flights to Suvarnabhumi Airport Thailand
- Cabinet cancels Suvarnabhumi metropolis project
- Deputy Prime Minister opposes Suvarnabhumi province plan
- Bangkok Airways says fare hike to Koh Samui was unavoidable
- International Pilots & Airlines reassure confidence for the new Bangkok airport, Suvarnabhumi
- Suvarnabhumi Airport city railway link set to open early next year
- JBIC interested in giving 5.6 Billion Baht loan for Suvarnabhumi Airport extension
- Suvarnabhumi airport railway link builder asked for deadline delay
- Engineer: Repairs some areas should take only 2-4 weeks
- Suvarnabhumi Airport to be opened on schedule
- Don Muang returns as Bangkok international airport
- Suvarnabhumi Airport needs expansion
- Airport of Thailand estimates B120 billion for noise compensation
- Airports of Thailand plans commercial complex land at Suvarnabhumi Airport
- State Railway given one month to finish Airport Rail Link plan
- Suvarnabhumi airport railway construction deadline to be decided this week
- New AOT Board should take immediate action to repair runways and taxiways at Suvarnabhumi Airport
- Flood dyke sinking, in need of repair
- Affirms readiness of Suvarnabhumi Airport by Transport Minister
- King Power denies its contracts abused law
- Airport Rail Link from Makkasan to Suvarnabhumi is way behind schedule
- New Bangkok Airport found taxiway problem last month 'caused by water'
- Suvarnabhumi Airport's Integrated Air Traffic Control System
- Airport Link railway system from Bangkok's inner city to Suvarnabhumi airport - News Update
- Don Muang To Become Maintenance Hub
- Transport Minister need more info on King Power Duty Free's contract termination
- Qantas Airways
- Star Alliance backs THAI stand on airport, 'two sites too costly'
- Thai Airways to keep international flights at Bangkok's Suvarnabhumi Airport
- Runways cracks not resulting from the construction - Airport of Thailand will meet the cost
- Sound-proof house for people living near Suvarnabhumi Airport
- Land near new Bangkok Airport can be used for logistics, expert says
- Transport panel will negotiate with residents affected by aircraft noise
- Airports of Thailand seeking a new President
- Airports of Thailand to reserve seats and toilets in Suvarnabhumi Airport for monks
- AOT affirms compensation to residents around Suvarnabhumi Airport
- Expansion of Suvarnabhumi airport starts soon
- Improving drainage systems around Suvarnabhumi Airport
- Suvarnabhumi will run smoothly as Don Muang within two months
- Suvarnabhumi Airport ready to be a gateway to Asia
- Compensation improved for property owners affected by aircraft noise
- Suvarnabhumi Airport - to become regional hub
- Airports of Thailand to make an initial 736 Million Baht for noise compensation
- Some air traffic must return to Don Muang
- Airport Features
- Customs free zone split up at Suvarnabhumi Airport will be reviewed today
- Transport Minister to take ambassadors tour Suvarnabhumi Airport
- King Power Duty Free may cut shop size at airport
- Meeting will be held to follow up problems at Suvarnabhumi Airport
- Suvarnabhumi Airport's Immigration officers undergoing 'personality training'
- Aircraft Insurance
- New board of Airports of Thailand to cover up loss during military government took control
- Singapore Airlines
- JAL to add flight after Suvarnabhumi Airport opens
- Transport Ministry says no return back to Don Muang
- Global aviation meeting to be held in Bangkok on June 28
- Jobs accelerating in communities neighbouring Suvarnabhumi
- Councillor to help residents near Suvarnabhumi with more appropriate land prices
- AOT seeks more foreign-denominated income
- Airport of Thailand to push airlines back to Don Muang airport
- New Bangkok Airport up and running
- Thailand to be aircraft maintenance centre of Asia
- Deputy Transport Minister set to wipe out taxi queue mafia
- Future opportunities for Suvarnabhumi
- Transport minister calls for higher security at Suvarnabhumi Airport
- Board of Thailand Airports has resigned
- Suvarnabhumi Airport Passenger Terminal Building
- Airports of Thailand may run own commercial area after terminating King Power contracts
- Flight times to Europe should be shortened by up to an hour
- Expected more foreign arrivals at Suvarnabhumi Airport
- Residents around Suvarnabhumi airport accept deal on noise problem
- Million-dollar toilets to be added at Suvarnabhumi Bangkok Airport
- Advance IT systems ready at Suvarnabhumi Airport
- Airports of Thailand to revoke permanent passes of all King Power staff
- Jetstar to Land at Suvarnabhumi Airport Friday, September 15, 2006
- Car Rental
- Thailand's visa-free entry rules tighten
- Suvarnabhumi ranks 4th best airport in online travel magazine poll
- Airport Special Campaign: Thai Culture & Lucky Passenger
- Airport of Thailand to promote Suvanabhumi as Smile Airport
- 46 Diplomats confident in Suvarnabhumi Airport's capability
- Moving to Suvarnabhumi
- Aircraft Maintenance
- New Airports of Thailand chief promoted
- European arrivals via Suvarnabhumi Airport rose year-on-year to 2.1 million
- Suvarnabhumi stands 6th in the 10 Most On-Time airports - ForbesTraveler
- AOT helps communities affected by noise pollution
- Airports of Thailand to study Don Muang as a 2nd Bangkok international airport
- Samitivej Srinakarin to open first private medical centre at Suvarnabhumi
- Novotel Suvarnabhumi Airport Hotel Opens
- New AOT board to sue King Power
- Thai Airways requests passengers check in 3 hours in advance
- New Bangkok Airport contracts to be re-examined by Gen Saprang
- Re-opened Don Muang may operate at loss in the beginning
- Private sector confident Suvarnabhumi’s cargo hub potential
- Suvarnabhumi Airport boosts investment
- Airport Express
- Malaysian Airline to start at Suvarnabhumi Airport on Sept 28
- Global Positioning System
- Public Bus
- Customs Department satisfied overall performance
- Trial for International Flights completed successfully
- Etiquette training for immigration officers at the new Bangkok Airport
- THAI Air to Migrate to Suvarnabhumi Airport
- Surging traffic puts former Bangkok Airport ahead of Hong Kong and Changi
- Demand for Novotel Suvarnabhumi Airport Hotel surged
- Private Vehicles
- Decorating the gateway to Southeast Asia
- Aircraft Sales
- Two-airport plan risk government's credibility
- New government to force fare meters in taxis to protect passengers
- Nok Air starts early at new airport but opts out on big day
- Aircraft Charters
- Air India to take off from Suvarnabhumi Airport
- In flight liquids to be strictly enforced on June 1, 2007
- No housing zone grows to 10km around Suvarnabhumi Airport
- Samui airport to become second international flight hub
- Dining at Suvarnabhumi Airport (Guide / Article)
- Thai Airways loses customers after moving back to Don Muang airport
- Air India
- Nok Air will move all flights from Suvarnabhumi Airport to Don Muang Bangkok Airport on March 24
- Airport Limousine
- Bangkok Airways first flight success
- Noise pollution around new Bangkok Airport will be concluded
- Malaysia Airlines
- Public Taxi
- Opening Suvarnabhumi Airports is not easy
- Thai Air starting first flight from Suvarnabhumi Airport today
- Private Buses
- Air Crew Coach
- New duty free shop operator at Suvarnabhumi Bangkok Airport could be delayed
- Tour Group (ATTA)
- Charter Flight
- Battle of the Airtropolises takes off
- Budget airlines submit flight plans Aug 17, 2006
- Suvarnabhumi expansion dates to be pushed forward
- Passengers will be welcomed with fresh Thai fruits at Suvarnabhumi airport
- Air traffic system in Suvarnabhumi Airport in place
- World's largest plane landed smoothly at Bangkok's Suvarnabhumi Airport
- Koh Samui tour operators protest sharp rise in airfares by Bangkok Airways
- Don Mueang Airport will turn to logistics hub
- Ten candidates apply for chief executive of Airports of Thailand
- Suvarnabhumi to build a low-cost passenger terminal costing 1.2 billion Baht
- IATA warned AOT on shifting some flights back to old Bankok Airport
- Suvarnabhumi Airport welcomes massive number of passengers
- Non-aviation services could make more revenue for AoT
- Bangkok voted as the best city leisure destination
- Travelers Assistance Center opens for New Year weekend holiday
- Suvarnabhumi airport security tightened during festive season
- CTX baggage scanners at Suvarnabhumi fully functional this week
- Contact
- Suvarnabhumi Public Transportation
- Airlines's Passengers Attention!
- New Airport fees for Suvarnabhumi Airport
- Energy-cutting measures at Suvarnabhumi help airlines save
- Thai Airways reshuffled ground service executives
- Thai Airways, American Express contract with UN agencies
- Passengers on first commercial flights satisfied with Suvarnabhumi Airport
- Airport Shuttle Bus
- Bangkok Airport Flight Schedules
- Suvarnabhumi Aerotropolis plan would have pros and cons
- Airports of Thailand told to buy land and buildings within 10km around airport
- Airports of Thailand board rejects plan to sell its stake in Airport Associate Co
- Amari Don Muang Hotel emphasizes meetings as customers move to the new airport (Guide / Article)
- Air Purification System
- Look back to the old Don Muang Airport (Article)
- Thai Airways sets up Call Center for passengers baggage claim
- Airport Fees
- Air passenger through Thailand's six major airports grew robustly in 2006
- International visitor arrivals increase at Suvarnabhumi Airport
- Don Mueang Airport reopened costs Airports of Thailand loss 70 Million Baht a month
- Thai Airways informs the opening of Suvarnabhumi airport to Korean citizens
- No Ceremonies for Don Muang close
- Airports of Thailand to cancel Suvarnabhumi Airport hotel contract
- Thai AirAsia switch to Suvarnabhumi early
- Land price rises near Suvarnabhumi
- Bonded warehouse area at Suvarnabhumi airport to be expanded
- Re-using of Don Muang International Airport
- One-Two-Go Airlines shifting flights from Don Muang to Suvarnabhumi Airport
- Thai Airways, Nok Air, One-Two-Go and Orient Thai, will resume services at Don Muang on March 25, 2007
- Civil Aviation Training Centre to supplying airport employee training
- Gallery
- Attractions around Suvarnabhumi Airport Prepared for Tourists
- Fingerprint identification equipment to be installed at Suvarnabhumi Airport
- Thai Airways receives 777-200ER from Boeing
- DCAP Confident Suvarnabhumi Airport will have Power
- CTX scanners have been fixed & ready for full operation









February 13th, 2007 at 11:10 pm
It is absurd for ASTV people to think that it should be closed for two years. The issue is not how long the SUVARNABHUMI Air Port should be closed for repair because in all scenarios, no one can guarantee that there will not be any recurrence of the damage or other dangerous defects.
The ASTV people neve seem to realize that they have only one choice to fight for, that is to permanently close it. Why would they want to risk the complete restoration which is much more expensive when they can also can’t legitimately guarantee that nothing would go wrong?
There are more than one kind of liability in this matter. Political liability is not the same as professional one. While the temporary government doesn’t have anything to lose in the former,I wonder if there is any third party such as insurance company who is willing to cover for the later?
I am for General Sprung